Free SAP S/4HANA Project Systems Questions

Question 1

Which organizational structures are mandatory for networks? Note: There are 2 correct answers to

this question.

A. Company code

B. Functional area

C. Controlling area

D. Business area

Answer A C

Question 2

You have activated the workflow for confirmation variances in SAP Project System.

Who is the receiver of this workflow item?

A. B. C. D. The person responsible for the work center

The person responsible for the superior WBS element

The person responsible for the network activity

The MRP controller for the network

Answer B

Question 3

In your project, you work with a network and external activities. You have created a purchase

requisition. The corresponding purchase order is created as well. Now, you increase the quantity of

the external activity.

How does the system support this scenario? Note: There are 2 correct answers to this question.

A. The system can be configured to automatically trigger a workflow to inform the purchasing

B. C. D. group.

The purchase order is automatically updated to match the new quantity when you save the

project.

The system automatically creates a new purchase requisition with the difference from the

original quantity.

The system automatically updates the original purchase requisition with the changed

quantity.

Answer A D

Question 4

You use networks and internal activities in your project. You have activated capacity requirements

and notice that one work center is overloaded. You have no authorization to change the work

center.

How can you reduce the overload of the work center? Note: There are 2 correct answers to this

question.

A. B. C. D. Trigger automatic capacity leveling inside the project planning board.

Shift activities backward or forward on the time axis where more capacities are available.

Maintain subordinate internal activity elements assigned to other work centers.

Increase the capacities of the work center in the project planning board.

Answer A B

Question 5

Which of the following actions can transfer actual costs for external processing? Note: There are 2

correct answers to this question.

A. Saving a service entry sheet

B. Saving a goods receipt

C. Saving a supplier invoice

D. Saving a purchase order

Answer A B